Hutto, TX case study · April 2026

City acceptance scope on a Hutto commercial subdivision

Developer / general contractor · Light industrial subdivision, Hutto off SH 130 · New Construction Sewer Verification

Sewer camera view of the same Hutto sanitary segment after flushing and correction, showing clean PVC ready for City acceptance
Sewer camera view inside a newly installed Hutto public sanitary segment showing construction debris before flushing
BeforeAfter

Drag the divider to compare. Before: Sewer camera view inside a newly installed Hutto public sanitary segment showing construction debris before flushing After: Sewer camera view of the same Hutto sanitary segment after flushing and correction, showing clean PVC ready for City acceptance

Footage inspected
1,140 ft
Segments
9
Resubmittals needed
1
Schedule recovered
~3 weeks

The problem on this Hutto site

The developer needed City acceptance on newly installed public sanitary before final plat and pad sales. A prior submittal had been rejected for incomplete video and unreadable footage, and every week of delay carried real carry cost.

How our NASSCO-certified crew approached it

  1. Reviewed the City's rejection notice first and built the inspection plan to its exact deliverable format
  2. Ran all 1,140 ft manhole to manhole with a mandrel check and post-flush scope on each segment
  3. Coded to PACP with continuous footage counters and legible headers on every segment
  4. Delivered indexed video, defect log, and manhole reports as one submittal package

What the camera documented

  • Three segments with construction debris that would have failed a City flow check
  • One deflected joint at 34 ft on a single segment, corrected before submittal
  • Manhole benches and channels acceptable across all structures inspected
  • Grade verified within tolerance on every remaining run

Measurable results

  • Accepted by the City on the first resubmittal with no further comments
  • Final plat cleared roughly three weeks earlier than the developer's contingency schedule
  • Defect list handled while the contractor was still mobilized, so no separate return trip

Need this on your Hutto project?

CSC Pipe Inspection runs commercial CCTV, jetting, hydro excavation and line locating across Austin and Central Texas with 25+ years of field experience and NASSCO/PACP-coded reporting.